Work Planned: August 2023
From Shawmut Design & Construction:
Throughout the month of August we will be pouring concrete slab on the job site. Our slab pour schedule is below (weather permitting).
We have a permit to close the section of Spring St. between Somerville Ave and Pitman Street for the day of pours. Access to 6, 8 & 10 Spring Street will be allowed by police detail.
Concrete will start at 7am and continue to 6-7pm depending on how the truck service is.
Concrete Pour Days
Monday 8/7/23
Wednesday 8/9/23
Friday 8/11/23
Thursday 8/17/23
Wednesday 8/23/23
Weekend work will continue intermittently throughout August.