Work Planned: August 2023

 From Shawmut Design & Construction:

  • Throughout the month of August we will be pouring concrete slab on the job site. Our slab pour schedule is below (weather permitting)

  • We have a permit to close the section of Spring St. between Somerville Ave and Pitman Street for the day of pours.  Access to 6, 8 & 10 Spring Street will be allowed by police detail.

  • Concrete will start at 7am and continue to 6-7pm depending on how the truck service is.

  • Concrete Pour Days

    • Monday 8/7/23

    • Wednesday 8/9/23

    • Friday 8/11/23

    • Thursday 8/17/23

    • Wednesday 8/23/23

  • Weekend work will continue intermittently throughout August.