Work Planned: September 2023
Below please find a list of planned construction activities at 599 Somerville expected during September 2023 from Shawmut Design & Construction:
Basement Concrete Slab Pour - Large 1x day pour which involves multiple trucks and will include the closure of Spring St. between Somerville Ave and Pitman Street for the day of pours. Access to 6, 8 & 10 Spring Street will be allowed by police detail. Tentative Date: 9/12/23.
Fireproofing of Steel - Cementitious spray applied to steel. Protection tarps will be installed for overspray.
Concrete Masonry Unit (CMU) West Elevation - Building CMU wall unit from inside site, protection installed on roof of abutter to west of job site. This work is expected to occur throughout the month of September.
Exterior Wall Frame, Board & Insulate - Begin to build exterior walls. This will include work close to the property line on lifts, we will be in touch with individual abutters as appropriate to discuss.
Stormwater Connection in Somerville Ave - Deep excavation in Somerville Ave will include the closure of a drive line on Somerville Ave during the day. We will be in touch with more specifics once dates are finalized in accordance to permits specifications issued by City of Somerville.
Windows Installed - Install windows per elevation. This work is estimated to last 2x days per elevation and will include a crane onsite. More details to follow re: dates of work planned.
Spring Street Closure Permit - Shawmut and the project has a street closure permit active for the week of .September 4th, 2023. Planned street closures have been scheduled for Thursday, September 7th & Friday, September 8th from 7am to 3pm, This closure is to accommodate large deliveries of additional materials to the site. Access to 6, 8 & 10 Spring Street will be allowed by police detail.
Weekend Work - Saturday work will continue intermittently throughout September.