Work Planned: July 2023
From Shawmut Design & Construction:
Steel erection will continue until mid/end of July 2023. Following the completion of the steel, we will be moving into placing concrete decks.
Starting in early August, we will begin fire proofing the steel beams and columns followed by facade erection.
Extended hours and Saturday work will be intermittent throughout July.