 From Shawmut Design & Construction:

  • Steel erection will continue until mid/end of July 2023. Following the completion of the steel, we will be moving into placing concrete decks.

  • Starting in early August, we will begin fire proofing the steel beams and columns followed by facade erection.

  • Extended hours and Saturday work will be intermittent throughout July.