Work Planned Week of 11/20
From Shawmut Design & Construction:
During the week of November 20th, 2023, there will be a lot of boom lift activity at Gate A as we continue to wrap the façade and prep for glass install.
No Spring St closures planned and we will have cones and flaggers in the street when moving any equipment.
The 599 Somerville jobsite will be open Monday-Wednesday, Friday and Saturday of this week.
We will be working this Saturday 11/25 on the exterior of the building and welding on the roof. Working hours will be from 9am-5pm.