Work Planned Week of 11/20

From Shawmut Design & Construction:

  • During the week of November 20th, 2023, there will be a lot of boom lift activity at Gate A as we continue to wrap the façade and prep for glass install. 

  • No Spring St closures planned and we will have cones and flaggers in the street when moving any equipment. 

  • The 599 Somerville jobsite will be open Monday-Wednesday, Friday and Saturday of this week. 

  • We will be working this Saturday 11/25 on the exterior of the building and welding on the roof.  Working hours will be from 9am-5pm.