Work Planned Week of 11/6

From Shawmut Design & Construction:

During the week of November 6th, 2023, we will have large deliveries to the 599 Somerville jobsite on Monday – Friday broken down below.  Spring St. will not be closed however there will be flaggers in the street at times when getting vehicles situated onsite.

  • Monday 11/6/23

    • Two cranes onsite both taking multiple deliveries to load material onto the roof and hang glass

  • Tuesday 11/7/23

    • Two boom trucks loading materials into the building

  • Wednesday 11/8/23

    • One crane loading materials onto the roof

  • Thursday 11/9/23

    • Excavation inside Spring St. Gate, will have multiple dump trucks hauling material

  • Friday 11/10/23

    • Excavations will continue