Crane Loading Chiller Units to Roof - 1/11/24

From Shawmut Design & Construction:

  • Please be advised that on Thursday, January 11, 2024 beginning at 7am, Shawmut will be working with Bosco Crane to load chiller units to the roof at 599 Somerville Ave.

  • The crane will be placed on Somerville Ave per approved permits & transportation management plan from the City of Somerville.  See graphic below.

  • Police details have been requested by Bosco Crane and Shawmut will have extra laborers on standby.  

  • This will be a full day operation.