Work Planned Week of 11/14
Sitework –
Construction of the elevated platform will continue through the week with majority of work ending by Tuesday (11/15)
Work consists of tri-axles and excavators delivering and spreading dense grade soil. Then periodic compactor use to stabilize the soil making it safe for heavy machinery.
The compactor use will be the most noticeable for the neighbors, but will only be used for short periods of time.
Excavation and placing of a drilling “guide wall” will commence on the north side. This will consist of excavators, mini plate compactors, and concrete trucks to place concrete.
Foundations –
Drilling and concrete placement of the secant piles will continue on the east side of the site.
We are anticipating that the crew will work some long days which may extend to but no later than 6:00 pm.
The most noticeable noise from drilling will come from the shaking of the drill.
Per soil management requirements, as we excavate through different soil classifications, we must separate the soil in different piles for removal off-site.