Work Planned: June 3 - 10th

From Shawmut Design & Construction:

  • During the week of June 3rd - June 10th, we will be erecting the Structural Steel for Phase #1 of 599 Somerville building on the western third of the job site (see graphic below). 

  • Additionally, our site contractor will be working on utilities in and around Spring St. 

  • Weekend work planned Saturday 6/3 & 6/10..

If you have questions, suggestions and or concerns, we'd love to hear from you, email us 599@rafiproperties.com. If you need to speak with someone regarding a potential safety concern with the job-site, please call the Shawmut Safety Hotline (877) 342-7233.